  • Helping keep the lights on for half a million Australians
  • A smart roadmap for transmission line relocation
    • 13/11/2018
    • A smart roadmap for transmission line relocation
    • Earlier this year, Zinfra was engaged by TransGrid to relocate a 2.4km section of its 330kV transmission line (TL24), including the removal of 12 existing steel towers and the installation of eight new steel towers situated on a new alignment, to enable the extension plans for the mine.

    • Read more
  • Moving mountains to keep the power flowing
    • 11/02/2019
    • Moving mountains to keep the power flowing
    • Replacing two transformers on Queensland’s second highest mountain while ensuring minimal interruption to the electricity supply is no mean feat, but Zinfra overcame several challenges to get the job done, using its significant experience in the power sector to gain practical completion on the project three months ahead of schedule.